Paving Schedule

Summer 2025 Paving Schedule

Thursday, July 17, 2025 - Chip Seal begins on the following roads:  
Chip Seal is a two-step process, the exposed aggregate "chip" will be micro-sealed to complete the process.  It will take approximately 3 weeks to complete, weather pending.  

  • Chestnut Hill Road
  • Florida Hill Road
  • Ramapoo Road
  • Overlook Drive
  • Kellogg Street
  • Millers Lane
  • Farm Hill Road
  • Nutmeg Court

 

Monday, July 21, 2025 - Paving begins on the following roads: 
The milling and paving  will take approximately 3-4 weeks, weather pending. 

  • Pine Mountain Road
  • Farrar Lane
  • Lounsbury Road
  • Dowling Lane
  • Ridgecrest Drive
  • Stonecrest Road
  • Ritch Drive
  • Filmore Lane
  • Stonewall Road
  • Old South Salem Road
  • Old Stagecoach Road (Bennetts Farm to Aspen Ledges)
  • Halpin Lane